Bond 2007: Status Report

Status Codes

D = In Design
B = Bidding
UC = Under Construction
C = Complete

Project

Original Budget

Current Budget

Increase
(Decrease)

Status

Notes

NEW SCHOOLS
Brennan HS $98,857,145 $97,282,172 -$1,574,973 C (1)
Garcia MS $41,548,442 $42,029,232 $480,790 C (1)
Briscoe MS $46,816,017 $45,023,293 -$1,792,724 C  
Kuentz ES $22,537,955 $21,135,283 -$1,402,672 C (1)
Langley ES $22,537,955 $20,729,639 -$1,808,316 C (1)
Hoffmann ES $22,537,955 $20,551,214 -$1,986,741 C (1)
Martin ES $22,867,956 $21,860,305 -$1,007,651 C  
Behlau ES $25,078,614 $22,374,757 -$2,703,857 C  
Henderson ES $25,078,614 $21,788,472 -$3,290,142 C  
Los Reyes ES $26,583,329 $25,063,329 -$1,520,000 UC  
Lieck ES $26,583,329 $25,256,177 -$1,327,152 C  
Mireles ES $26,583,329 $25,935,865 -$647,464 C  
Allowance $0 $0 $0    
Sites $20,000,000 $20,000,000 $0    
ADDITIONS
Jay HS $8,994,940 $8,906,415 -$88,525 C  
Warren HS $10,525,000 $8,064,807 -$2,460,193 C  
Pease MS $11,759,320 $10,122,930 -$1,636,390 C  
Rayburn MS $12,373,000 $11,646,470 -$726,530 C  
Adams Hill ES $9,769,730 $7,783,230 -$1,986,500 C  
Meadow Village ES $5,289,560 $3,634,402 -$1,655,158 C  
Ward ES $3,385,050 $3,275,735 -$109,315 C  
RENOVATIONS
Marshall HS $9,679,305 $10,643,903 $964,598 C  
Taft HS $1,917,120 $2,002,747 $85,627 UC  
Zachry MS $0 $41,409 $41,409 C  
Glenn ES $11,958,225 $9,936,884 -$2,021,341 C  
Oak Hills ES $4,641,630 $4,130,880 -$510,750 C  
HIGH SCHOOL BAND ASPHALT
Holmes, Jay, Marshall HS $900,000 $1,282,507 $382,507 C  
PE/LOCKER ROOMS
Clark, Holmes, Jay HS $2,610,000 $2,610,000 $0 C  
KITCHENS
Ross MS $1,500,000 $1,194,995 -$305,005 C  
Zachry MS $1,000,000 $1,099,328 $99,328 C  
Howsman ES $800,000 $883,000 $83,000 C  
Villarreal ES $800,000 $1,045,882 $245,882 C  
LIBRARY ADDITIONS
Neff MS $1,802,485 $1,795,357 -$7,128 C  
Pease MS $300,000 $300,755 $755 C  
Rayburn MS $300,000 $302,785 $2,785 C  
Cable ES $1,307,515 $1,225,781 -$81,734 C  
SCIENCE LABS
Clark HS $12,989,700 $11,157,201 -$1,832,499 C  
Holmes HS $12,989,700 $11,532,918 -$1,456,782 C  
INFRASTRUCTURE PROJECTS
  $40,000,000 $42,324,198 $2,324,198 UC  
ELEMENTARY PLAYGROUNDS
ADA Access to Playgrounds $1,380,000 $2,023,778 $643,778 C  
Playground Upgrades $970,000 $738,009 -$231,991 C  
GYM AIR CONDITIONING
High School Gym A/C $4,768,600 $3,985,735 -$782,865 C  
Middle School Gym A/C $6,554,000 $7,502,798 $948,798 C  
ROOFING PROJECTS
  $13,605,900 $11,099,124 -$2,506,776    
OTHER PROJECTS
Technology 42,188,580 42,188,580 0    
Buses 20,000,000 20,000,000 0    
Reimburse General Fund  (1) 8,000,000 8,000,000 0 C 1
Contingency Fund 0 31,157,719 31,157,719    
TOTAL $692,670,000 $692,670,000 0    

Notes

1. Project design fees funded from General Funds for:

Brennan HS $3,500,000
Garcia MS 1,800,000
Kuentz ES 900,000
Langley ES 900,000
Hoffmann ES 900,000
  $8,000,000