2004 : Additions & Renovations
|
Burke ES Nine Classroom Addition. Notice to Proceed issued on April 18, 2005. Contractor is completed with the building pad foundations and is moving forward with building steel erection for the Classroom Addition. 100% Complete |
Cost: $2,035,322* Construction: 03/2005 to 06/2006 Architect: Kell Munoz Contractor: Kencon Constructors Client Contact: Thomas Curiel |
|
Glenn ES Music Room Addition and Art Room Remodeling. Notice to Proceed issued on September 6, 2005. Contractor mobilized on site and is moving forward with demolition work in the existing building and proceeding with the new building pad excavations. 100% Complete |
Cost: $715,956* Construction: 07/2005 to 06/2006 Architect: Madeline Anz Slay Architecture Contractor: Satterfield and Pontikes Construction Client Contact: Mary Helwick |
|
Hobby MS Kitchen, cafeteria, fine arts and library renovations. notice to proceed issued on May, 26 2006. Band hall, orchestra room, kitchen addition, choir room and interior classroom renovations are substantially complete. 100% Complete |
Cost: $4,138,814* Construction: 04/2006 to 07/2007 Architect: Chunney & Associates Contractor: PECO Construction Client Contact: Marilyn Sevedge |
|
Howsman ES Administration office remodeling to meet NISD standards. 100% Complete |
Cost: $452,117* Construction: 12/2005 to 07/2006 Architect: 2Ten Architects Contractor: Alpha Construction Client Contact: Victor G. Valdez |
|
Jay HS Renovation of existing classroom space into 14 science lab/lecture rooms. Notice to proceed issued on may 18, 2006. The project is substantially complete and the contractor is in the process of completing a small number of mechanical and architectural punch list items. 100% Complete |
Cost: $4,774,424* Construction: 05/2006 to 07/2007 Architect: Alamo Architects Contractor: Suburban Construction Client Contact: Kathy Weaver |
|
Jones MS Library addition and interior rennovations. Notice to proceed issued on May 5, 2006. Project is substantially complete. 100% Complete |
Cost: $3,616,064* Construction: 03/2006 to 06/2007 Architect: O'Connell Robertson & Associates, Inc. Contractor: David and David Construction Client Contact: Marilyn Sevedge |
|
Leon Valley ES Nine classroom addition, interior remodeling and parking expansion. 100% Complete |
Cost: $2,668,967* Construction: 01/2006 to 04/2007 Architect: Jesse Garza, AIA Contractor: Suburban Const. Client Contact: John Amos |
|
Mary Hull ES Nine classroom addition, classroom renovations and site work. Notice to proceed issued on March 10, 2007. Contractor is completed with exterior wall and window replacement at the existing classroom buildings. The building addition foundation pad is complete with plubming rough-in and steel placement is in progress. 100% Complete |
Cost: $3,713,098* Construction: 02/2007 to 05/2008 Architect: Garza Architects Contractor: WR Griggs Construction Client Contact: Thomas Curiel |
|
Nellie Reddix Center Office and Classroom Addition 100% Complete |
Cost: $1,764,442* Construction: 07/2005 to 08/2006 Architect: Paul Molina Architects Contractor: CA Landry Client Contact: Victor G. Valdez |
|
Pease MS Courtyard improvements and 2,000 sq. ft. kitchen addition to accommodate additional serving lines, increased cooler and freezer space, dry storage, and food preparation area. Notice to proceed issued on December 1, 2006. Project is substantially complete. 100% Complete |
Cost: $1,756,111* Construction: 11/2006 to 07/2007 Architect: 2Ten Architects Contractor: Baron-Long Contractors Client Contact: Victor G. Valdez |
|
Raba ES Seven classroom addition, additional parking and playground improvements. Notice to proceed issued January 3, 2007. The building concrete foundation and columns are complete. Upper concrete beams are in progress. Playground improvements and parking area addition are also in progress. 100% Complete |
Cost: $1,965,260* Construction: 12/2006 to 12/2007 Architect: Noonan Rittimann Architects Contractor: FA Nunnelly Client Contact: Thomas Curiel |
|
Ross MS Seven classroom addition, interior renovations and parking expansion. Notice to proceed issued on June 26. Science lab addition and administrative area renovations are substantially complete. Building C science lab renovations are in progress. Reconstruction of the staff and visitor parking area in front of school is in progress. 100% Complete |
Cost: $5,207,924* Construction: 04/2006 to 11/2007 Architect: Alamo Architects Contractor: MJ Boyle Client Contact: Kathy Weaver |
|
Rudder ES Library addition, interior renovations and mechanical upgrades. Notice to proceed issued on April 26, 2006. The library addition, new counselor's office suite, nurse clinic, teacher workroom and administration area renovations are substantially complete. 100% Complete |
Cost: $2,998,324* Construction: 03/2006 to 07/2007 Architect: O'Neil Conrad Oppelt Contractor: W. R. Griggs Construction Client Contact: Kathy Weaver |
|
Stevenson MS Fine Arts Addition, misc. Interior Renovations, Kitchen Addition, Library Renovations, Six (6) Classroom Addition, Wood Shop and Industrial Technology Lab Addition, Site Work and HVAC upgrades. Phase III of the Interior renovations at the second floor are nearing completion. The new building addition is now dried in with the roof , CMU walls, interior walls and MEP rough-in in progress. New parking area in progress. Library Addition roof joist and decking installed. Kitchen/Serving Line and Administration Renovations in progress and scheduled to be completed in August. 100% Complete |
Cost: $9,046,878* Construction: 06/2004 to 12/2005 Architect: Kell Munoz Contractor: Bartlett Cocke Client Contact: Thomas Curiel |
|
Timberwilde ES Interior Classroom and Office Remodeling. Work in progress and scheduled to be completed in early August. 100% Complete |
Cost: $440,876* Construction: 04/2005 to 07/2005 Architect: SA Partnerships Contractor: Alpha Building Corporation Client Contact: Thomas Curiel |
|
Warren HS Seventeen Classroom Addition, Site Improvements and Office Additions. Contractor has completed interior rennovations and placement of the first floor concrete slab at the classroom addition. Column forming for the second floor in progress. 100% Complete |
Cost: $3,410,554* Construction: 04/2005 to 05/2006 Architect: Garza Bomberger Contractor: Satterfield & Pontikes Construction Client Contact: John Amos |